| 1 | Faculty obtained (21 April 2004) |
| 2 | Prepare bells for lifting out of tower |
| 3 | Remove tie rods and prepare frame for de-construction |
| 4 | Lift bells and part of the frame out of tower, lift up joists, beams, and lead |
| 5 | Prepare templates for sound control panels |
| 6 | Remove clock to a place of safety |
| 7 | Cut access panel through ceilings so that bell frame can be removed |
| 8 | Remove remaining bell frame |
| 9 | Measure up for the new bell frame |
| 10 | Remove existing timber roof |
| 11 | Install new timber roof |
| 12 | Install lifting and shifting beams |
| 13 | Lay lead work to roof |
| 14 | Extend and finish access panel through floors of new bell and clock chambers |
| 15 | Lay new boarding to bell and clock chamber floors |
| 16 | Install new ringing gallery floor with access panel and balustrade |
| 17 | Install guards to west window |
| 18 | Construct new bell frame at Whitechapel |
| 19 | Make and install sound control panels |
| 20 | Cast two new bells |
| 21 | Cut and form padstones for new bell frame |
| 22 | Install new bell frame |
| 23 | Install electricity to tower with emergency lighting |
| 24 | Make good holes around frame members |
| 25 | Bless new bells before they are hung |
| 26 | Hang bells |
| 27 | Fit controls to sound panels |
| 28 | Make good walls to ringing gallery and decorate |
| 29 | Restore and re-fix peal boards and other plaques |
| 30 | Clear out and clean all chambers in the tower |
| 31 | Install clock with auto-wind facility |
| 32 | Re-dedication by the Bishop (10th January 2005) |